Welcome to the Ocean Park Pizza Redevelopment Project page. On this page are the pictures, videos and information about the project development as it progressed. The project started on April 25, 2005 with the closing of the old restaurant and a new beginning emerged on May 26, 2006 when the Ocean Park Pizza Restaurant and Steak House and Ocean Park Pub welcomed their first customer.

To view the photographs or the videos, simply click your mouse on the date beside the description you want to see.

Click Here to View a Directory of the Suppliers and Trades

DATE
Video
Description
June 22, 2006 EPILOGUE   We take a final look at the Ocean Park Pizza Restaurant and Steak House and the Ocean Park Pub in the brilliant June sunshine.
June 17, 2006 GRAND OPENING!   As part of the OCEAN PARK DAY, the Ocean Park Pizza Restaurant and Steak House and the Ocean Park Pub celebrated its Grand Opening. Judy Higginbotham, Cith Councillor, representing the Mayor of Surrey, cut the ribbon for the official opening. This event happened to coincide with the World Cup Soccer and so the Pub was particularly popular.
June 17, 2006 GRAND OPENING! As part of the OCEAN PARK DAY, the Ocean Park Pizza Restaurant and Steak House and the Ocean Park Pub celebrated its Grand Opening. Judy Higginbotham, Cith Councillor, representing the Mayor of Surrey, cut the ribbon for the official opening.
May 26, 2006 OPENING NIGHT!   Welcome to the Ocean Park Pizza Restaurant and Steak House and the Ocean Park Pub! Come meet the first customer; Jock Bray, the waitresses and bartenders and perhaps you might recognize some friends of yours who were lucky enough to be there on this joyous occasion.
May 26, 2006   There are lots of signs of an impending opening. There are boxes being opened, bottles are being put on shelves, glasses are being stacked, and even though Darrell and Gerry are busy installing more trim, by the end of the day, they start packing up.
May 25, 2006   There is new lawn around the front of the building, all the chairs for the restaurant arrive, the kitchen crew test out the chip fryer, the soda dispensers get tested and calibrated, Darrell is installing more trim and Gerry is installing more millwork around the bar.
May 24, 2006   Ves is sand-blasting an engraving into the boulder by the bench, Ray is installing booth tables, Darrell are installing hand-rails, Gerry is installing more millwork, chairs are arriving and SYSCO arrives with its first food order.
May 23, 2006   Ray and Josh are assembling tables, Lotto BC is installing flat panel TVs for Keno and animated horse racing, Mark is continuing with touch-up painting, James and Darrell are installing more millwork and Gerry and James install all the outside signs.
May 22, 2006   Advanced Integration has installed the flat panel TVs, Mark is doing touch-up painting, Ray is installing pot lights over the bar and Darryl is installing a video camera.
May 20, 2006   Darrell is installing beams in the pub, Mark is staining the beam boards, the electricians are installing track lighting over the bar and Doug is installing the cooler cabinet doors.
May 19, 2006   We meet Rob Kay of Kay Design who did the interior design, Mark is staining beam boards, Darrell, Gerry, Dan and Matt install the pub fireplace mantel and a foot rail for one of the pub seating areas arrives.
May 18, 2006   The lights are installed in the parking lot, the lines for parking are painted, the wrought iron window bars are installed, the wood trim crew is installing more beams and trim, and Kevin installs the beer tap bridge with no less than 12 beer taps.
May 17, 2006   The wood trim crew is installing more beams and trim, Vern is plumbing more bar sinks, and the electricians are installing the main hall chandeliers.
May 16, 2006   We tour the landscaping around the building, Vern is plumbing the bar sinks, and the finishing crew has installed the countertop on the cabinets around the bar cooler.
May 15, 2006   Nate is watering the plantings, Richard and Gerry discuss a feature to be installed at the corner of 128A street and 16th avenue, Mark is painting vents and the finishing crew is making progress with the wood trim.
May 14, 2006   This is a special Mother's Day tour as the landscaping is almost finished. Nate is planting the many small potted plants and we take a walk around the building to see the many trees and colourful flowers.
May 12, 2006   The landscaping continues with Richard and Nate distributing topsoil; Adam works on the lighting in the pub, Darrell and Tracy are installing sound speakers and the woodwork crew is making progress on the washroom stalls and beams.
May 11, 2006   The landscaping begins in ernest; Graeme plants a tree, Richard uses the backhoe to dig out a planter, Darrell installs a stub wall in the pub, and Mark is working on the paint edging.
May 11, 2006 Richard uses the backhoe to tear up some pavement and then to dig a planter.
May 11, 2006 Richard and Graeme plant a tree. Richard uses the backhoe to dig the hole and then to lift the tree to it. Graeme breaks open the root ball and then shovels the dirt around it.
May 9, 2006   Rob installs cedar vents in the garbage bin garage, Rian installs facia boards between the roof rafters, the woodwork finishing crew installs facia boards on the glulam beam in the pub, and Richard and Graeme begin the landscaping.
May 8, 2006   We get to look at the new outside lights, Mark prepares the garbage bin garage doors for painting, the woodwork finishing crew installs facia boards on the beam in the restaurant and we get a look at one of the beer tap handles that will go in the pub.
May 5, 2006   We tour all the outrigger installations, the cooler gets modified for matching up to the drink cabinets, we get an exclusive sneak preview of some of the products to be served in the pub and Rian is installing the shingle siding on the garbage bin garage
May 4, 2006   Rian and Mike are installing the shingle siding over the pub entrance doors, Rob is installing door thresholds, Martin is installing the light fixtures in the pub terrace and Sean installs an outrigger at the peak of the office dormier.
May 3, 2006   Rian is almost finished the shingle siding over the 128A street doors, Jarrod is grouting the joint between the slate border and the fir floor around the bar, Gerry and Matt have installed more real faux beams and an outrigger has been installed over the pub entrance.
May 2, 2006   Rian is working on the shingle siding over the 128A street doors, Gerry and Matt are installing more real faux beams and the outriggers for the roof peaks have been cut and painted.
May 1, 2006   The granite counter top for the bar is being ground to fit, Rian has completed the shingle siding over the main entrance, Sean is installing the final trim pieces over the main entrance and the outriggers for the roof peaks are being made.
April 28, 2006   Rian has almost completed the shingle siding over the main entrance, Sean has installed the strapping over the pub entrance and Geoff and the crew have installed the glass panels over the pub terrace.
April 27, 2006   Vern is installing the washroom sinks, Gerry and Matt are installing the bar cabinets, Sean is installing strapping over the pub entrance and Geoff and the crew are installing the glass panels over the pub terrace.
April 26, 2006   Rob is installing trim over the 128A street doors, Ray and Sean are installing the curved trim over the pub entrance, Gerry is installing the faux beams and the front doors have been installed.
April 25, 2006   Shawn wires up a speaker in the men's washroom, Ray and Sean are installing the trim over the pub outside door and Ronny and Alan install the bar's granite counter tops.
April 24, 2006   Archie pulls wires through conduit for the parking lot bases, Ray is installing the trim over the kitchen outside door and we get a look at the finished wainscotting and trim around the restaurant booths and a pub seating area.
April 22, 2006   The crew from Versatile Concrete add texture and colourant to the concrete area at the entrance to the parking lot and some of the entrance sidewalks have been sealed.
April 21, 2006   Sean and Rob are framing up a concrete form for a planter, Ray is installing the curved trim over the main entrance windows, Adam is installing the puck lights on the bar and Mark is painting the stairway walls.
April 20, 2006   Scott and Brian are oiling the reclaimed fir floor, Gerry is installing the kick panels on the bar cabinets and Rob is installing the metal doors on the garbage bin garage.
April 20, 2006 VIDEO: Brian and Scott, from Meyer Hardwood Floors, oil the Pub's reclaimed fir floor.
April 19, 2006   Rob and Sean are framing up a concrete form for the parking lot entrance, the flooring crew are sanding the pub reclaimed fir floor, Gerry is installing more wood trim on the wainscotting panels and David is pressure washing the concrete terrace and sidewalks.
April 19, 2006 VIDEO: David, from Versatile Concrete, power washes the terrace floor.
April 19, 2006 VIDEO: The crew, from Meyer Hardwood Floors, uses power orbital sanders to finish the Pub's reclaimed fir floor.
April 18, 2006   Rob and Sean are framing up a concrete form for a sidewalk, Gerry is putting a hearth on the terrace fireplace, Justin is pointing the rock facing for the pub fireplace, Gerry is installing more wood trim on the wainscotting panels and the concrete is poured for the terrace and the sidewalks.
April 18, 2006 VIDEO: The crew from Pioneer Paving pave the parking lot.
April 18, 2006 VIDEO: The crew from Versatile Concrete with help from RMC ReadyMix pour the concrete for the terrace and sidewalks.
April 17, 2006   Rob and Richard are preparing an area for a planter between the Ocean Park Dental building and the Ocean Park Pizza building, Marvin and Sean are framing up the concrete forms for sidewalks at the front, Gerry and Justin are installing the rock facing for the pub fireplace and John and Gerry are installing more wood trim on the wainscotting panels and around the windows.
April 17, 2006 VIDEO: Rob uses a sledge hammer to break up the paving in the Ocean Park Dental building parking lot to prepare the area for a planter.
April 17, 2006 VIDEO: Justin mixes a batch of mortar.
April 17, 2006 VIDEO: Gerry installs the corner pieces of the rock facing for the pub fireplace.
April 13, 2006   The excavation and paving crews are preparing the parking lot for paving, Gerry and Justin are installing the rock facing for the pub fireplace and John and Gerry are installing more wood trim on the wainscotting panels.
April 13, 2006 VIDEO: The parking lot is prepared by catapillar and compactor for paving.
April 12, 2006   Bob and Jeff are installing the gutters and downspouts, Adam is installing the outside light fixtures, David, and Willy finish installing the reclaimed fir flooring in the pub, Howard is installing carpet in the upstairs pub area and John and Gerry are installing more wood trim on the wainscotting panels.
April 12, 2006 VIDEO: Jay uses a Bobcat to level the ground around the side and front of the building.
April 11, 2006   Doug and Adam are installing the light fixtures in the pub area, Sieg, David, Henry and Willy are installing the reclaimed fir flooring in the pub, Rian is installing more cedar shingles on the pub terrace walls and John and Gerry are installing more wood trim on the wainscotting panels.
April 11, 2006 VIDEO: David installs the reclaimed fir flooring in the pub area.
April 10, 2006   Tim and Lawrence install the restaurant and pub booths and seating areas, Ray and Jarett install wood trim around the pub terrace door, Rian installs cedar shingles over the pub terrace and Mike installs the hardiplank shingles on the Ocean Park Dental building side.
April 10, 2006 VIDEO: Lawrence and Tim install one of the back rests for the seating in the pub area.
April 7, 2006   Mark does touch-up painting and the spray painting of the steel plates in the upper pub area, Brad, Ray and Jarett install strapping and hardiboard around the kitchen doors, Mike installs the hardiplank shingles on the Ocean Park Dental building side and Sean installs soffitting over the pub parking lot entrance.
April 6, 2006   Jarrod has installed the grout in the slate border around the bar and is now wiping off the excess grout, Jarett is working on the trim on the front side, Rian installs the cedar shingles by the terrace and Sean installs soffitting over the restaurant entrance.
April 6, 2006 VIDEO: Jarrod wipes away the excess grout around the slate at the base of the bar.
April 5, 2006   Jarrod has installed the slate border around the slate in the pub parking lot entrance, Jarett installs strapping on the front side, Rian installs the cedar shingles by the terrace and we look at some of the finish wood work inside.
April 4, 2006   We get a look at the cooler at the bar, Jarrod has installed the slate border and foot rests around the bar and the main entrance, Brad and Jarett install trim and strapping by the main entrance, Rian continues with installing the cedar shingles around the front of the building and Justin acid washes the rock facing on the garbage bin garage.
April 3, 2006   We get a look at the washroom floors which are stained and textured concrete, Jarrod has installed the slate border to fit around the bar and the main entrance, Brad and Jarett install trim on the main entrance posts, Rian is now installing the cedar shingles around the front of the building and Sean installs more soffitting.
March 30, 2006   Jarrod cuts slate pieces to fit around the bar, Rob installs more tile in the kitchen, Brad installs trim on the restaurant entrance posts and Sean installs more soffitting.
March 30, 2006 VIDEO: Jarrod cuts pieces of slate to fit around the base of the bar.
March 29, 2006   Howard installs the linoleum on the bar area floor, Jarrod installs grout into the coloured tile borders in the washrooms, Gerry continues with the wainscotting panels and Sean installs more soffitting.
March 29, 2006 VIDEO: Jarrod finishes the grout on the coloured tile border in the men's washroom.
March 28, 2006   Jarrod and Rob continue with the slate in the main entrance and the parking lot entrance to the pub, John and Gerry start installing the steel panels on the base of the bar, Leo continues with the wainscotting in the upper pub area and Rian installs more cedar shingles on the outside walls.
March 28, 2006 VIDEO: Howard prepares the bar area plywood sub-floor for installation of the linoleum.
March 27, 2006   Jarrod and Rob lay pieces of slate in the main entrance and the parking lot entrance to the pub, Marvin installs plywood backing in the washrooms, a huge load of the millwork arrives, John, Gerry and Leo continue with the wainscotting and Rian installs more cedar shingles on the outside walls.
March 27, 2006 VIDEO: Jarrod and Rob install the slate tiles in the main entrance.
March 25, 2006   Mark paints the steel plates on the wood beams.
March 25, 2006 VIDEO: Mark paints the steel plates on the wood beams.
March 24, 2006   A look at the beautiful tile in the washrooms, Ray and Jarret install more plywood sub-floor and more outside walls are finished with shingle siding.
March 23, 2006 VIDEO: Gerry and John cutting and installing panels for the wainscotting.
March 23, 2006 VIDEO: Scott demonstrates the mini-backhoe.
March 23, 2006   Jarrod and Mark continue with the tile in the washrooms, Ray and Alan install plywood on the bar floor and Gerry and John install the panels for the wood wainscotting.
March 22, 2006   Jarrod and Mark start installing the tile in the washrooms, Mark does touch-up painting in the pub, Ray installs plywood around the bar and the electricians wire up the bar.
March 21, 2006   Mark does touch-up painting in the main hall, Ray installs plywood backing in the washrooms and some of the bar cabinets are installed.
March 20, 2006 VIDEO: Cutting and installing tile in the kitchen.
March 20, 2006 VIDEO: Cutting a tile around an electrical box in the kitchen.
March 20, 2006 VIDEO: Rian installs the cedar shingles.
March 20, 2006   The interior wood doors are being installed, there is great progress with the tiles in the kitchen, Rob demonstrates how to cut tiles around electrical boxes, Rian puts up more shingles, and Sean installs more soffiting.
March 19, 2006 VIDEO: Mark and Tim stain the wood beams.
March 19, 2006   Mark and Tim stain the wood beams.
March 18, 2006 VIDEO: Tim scrubs the wood beams in preparation for staining them.
March 18, 2006 VIDEO: Mark patches the ceiling in the main hall.
March 18, 2006   Mark patches the ceiling in the main hall and Tim cleans the beams in preparation for staining them.
March 17, 2006 VIDEO: Jarrod installs tile in the kitchen.
March 17, 2006   Jarrod installs tile in the kitchen, the base of the bar has arrived, Sean installs the last of the steel plates on the beams and we get a look at Ocean Park Village from the roof.
March 16, 2006 VIDEO: The paving of the patch by the Ocean Park Pizza restaurant on 128A Street.
March 16, 2006   Sean installs the final steel plates on the wood beams in the pub area, Gerry and Justin are now working on the rock facing on the terrace fireplace, Jarrod is installing tiles in the kitchen, a handrail is being welded into place, and a paving crew is paving the patch on 128A street.
March 13, 2006 VIDEO: Justin is pointing the joints in the rock facing on the terrace front wall.
March 13, 2006 VIDEO: Mark is painting the upstairs office.
March 13, 2006 VIDEO: An inside look at the concrete mixer.
March 13, 2006   Sean and Tom continue with the installation of the wood beams in the pub area, Gerry and Justin are making excellent progress on the rock facing on the terrace front wall and and Rian has installed enough cedar shingles to show what the building will look like when finished.
March 10, 2006 VIDEO: Sean and Tom install steel plates on the wood beams.
March 10, 2006 VIDEO: Tom measures and cuts the wood beams.
March 10, 2006   Sean and Tom continue with the installation of the wood beams in the main hall and pub area, Gerry and Justin are working on the rock facing on the terrace front wall and and Rian starts installing the cedar shingles.
March 9, 2006 VIDEO: Tom, Sean and Rob are installing the wood beams in the main hall.
March 9, 2006   The wood beams are being installed in the main hall and pub area, Gerry and Justin continue with the rock facing on the terrace chimney and the posts by the restaurant front entrance and Rob installs horizontal strapping for the cedar shingles.
March 3, 2006 VIDEO: Justin is pointing the rock joints on the terrace chimney while Gerry continues with the rock facing on the terrace chimney.
March 3, 2006   The garbage bin garage roof gets its rafters painted black, Gerry and Justin continue with the rock facing on the terrace chimney, and the drywall crew is now sanding the drywall in the main hall.
March 2, 2006   Gerry and Justin install rock facing on the terrace chimney, Rob works on the outside wall strapping and the drywall crew continues with mudding the main hall.
February 28, 2006 VIDEO: The drywall crew give the main hall another coat of mud.
February 28, 2006   Gerry and Justin finish the rock facing on the pub chimney, and the drywall crew continues with mudding the main hall and installing drywall panels in the basement.
February 27, 2006 VIDEO: The drywall gets a coat of mud.
February 27, 2006 VIDEO: Gerry and Justin start rock facing on the pub chimney.
February 27, 2006   The garbage bin garage roof gets shakes, Gerry and Justin start rock facing on the pub chimney, and the drywall crew continues with mudding the main hall. P.S. Its Rob's Birthday!
February 24, 2006   The garbage bin garage roof gets all of its rafters, Sean of the drywall crew installs drywall pieces around the kitchen ducting and the terrace wall gets its capstones.
February 23, 2006   The garbage bin garage gets a plywood roof, and Garey of the drywall crew starts to apply drywall tape and mud to the drywall joints.
February 22, 2006   Dan and Rob install the rafters on the garbage bin garage and the drywall crew make blistering progress on the main hall and restaurant area.
February 21, 2006   The garbage bin "garage" is getting framed, the sidewalk is compacted in preparation for concrete, Gerry, the mason works on the pub chimney and Justin points the rock pillars.
February 15, 2006   Gerry, the mason works on the pub chimney and the BC Hydro crew installs the Ocean Park Village Pizza Restaurants hydro station.
February 14, 2006   Trenches are dug to install the street light bases and electrical pipes for 128A street and drywall is delivered.
February 10, 2006 VIDEO: A Bobcat is used to smooth the entrance to the parking lot.
February 10, 2006   A Bobcat is used to smooth the entrance to the parking lot, plastic vapour barrier starts getting installed over the insulation and Rob installs a door frame.
February 9, 2006 VIDEO: Gerry, the mason, works on the concrete capstones.
February 9, 2006 VIDEO: The electrician installs wiring in a electrical box.
February 9, 2006 VIDEO: The insulation and vapour barrier are being installed.
February 9, 2006   The fireplace units are installed, the capstone forms are filled, insulation is installed and the plumber solders some copper pipes.
February 8, 2006 VIDEO: The concrete curbs are poured and now the retaining pins are removed.
February 8, 2006   The curbs are poured, concrete forms are installed by Gerry the mason for capstones and Rob installs backing for the wood beams.
February 7, 2006   A look at the pub fireplace framing and the concrete forms for the new street side curbs on 128A street.
February 6, 2006 VIDEO: Installation of the grease pit unit.
February 6, 2006   Installation of the grease pit unit and and look at the soffeting.
February 2, 2006   Roy arrives with his concrete pumper truck to put concrete into the basement stair forms and the wall forms for the terrace.

January 30, 2005

VIDEO: The mason working on the rock facing on the outside walls by the terrace.

January 30, 2005

  The rock facing on the outside walls is progressing around to the front and by the terrace. Rob and Humphrey on on top of the world.

January 26, 2005

  More work on the rock facing on the outside walls, Rob works on the pub fireplace framing and Humphrey works on the concrete forms for the pub terrace.

January 24, 2005

  More work on the rock facing on the outside walls and progress on the terrace and grounds.

January 20, 2005

  More work on the rock facing on the outside walls and Rob and Humphrey work on framing the pub fireplace.

January 18, 2005

  Watch the mason work on the rock facing on the outside walls. Learn how to point and brush.

January 5, 2005

  Installation of the stone caps for the rock facing on the outside walls and work on the plumbing and heating systems.

December 30, 2005

 

More work on the building's mechanical systems by the plumbers. Watch them soldering copper pipes.

December 28, 2005

  Work on the building's outside walls begins in preparation for the rock facing and shingle siding.

December 23, 2005

  Watch the machines hard at work installing a concrete drainage channel for the parking lot.

December 13, 2005

  More work on the building and parking lot drainage, plumbing and heating systems.

November 28, 2005

  Installation of building and parking lot drainage and plumbing systems.

November 18, 2005

  The roof now has cedar shakes, the outside trim is being painted black and the windows are mostly in place.

November 10, 2005

  The roofers put on the last section of cedar shakes by the Ocean Park Dental building and the trim is being painted black.

November 04, 2005

  The roof has cedar shakes except for the side by the Bank of Montreal and Rob puts in more blocking.

November 01, 2005

  Most of the roof now has cedar shakes and the framing crew continues with putting in the floor and steps of the pub area.

October 26, 2005

  One whole section of the roof now has cedar shakes and the framing crew continues with the rafter ends.

October 25, 2005

  More shakes on the roof and the framing crew builds the backing for the rock columns.

October 24, 2005

  The beginning of shakes on the roof, plumbing, wiring and the terrace gets rafters.

October 12, 2005

  A look at the interior around the kitchen.

October 7, 2005

  More rafters ends, and the kitchen chimney takes shape..

October 1, 2005

  The building starts to have a major presence in the village.

September 27, 2005

  Adding rafter ends and delivery of beams for the terrace.

September 21, 2005

  Progress on the roof sheathing and blocking.

September 14, 2005

  The water main and a new hydro pole get installed, and work on the roof. Check out the view!

September 8, 2005

  More work on trusses and rafters.

September 2, 2005

  The roofline takes form as the trusses are installed.

September 1, 2005

  The trusses arrive.

August 16, 2005

  Wall sheathing is installed.

August 11, 2005

  Back filling of foundation and main floor framing.

August 8, 2005

  More progress on main floor framing.
August 4, 2005   Starting the framing of the main floor.

August 3, 2005

  Sub-floor continues, materials for main floor framing arrives.
July 29, 2005   The sub-floor goes on.
July 27, 2005   Installing main floor joists.
July 25, 2005   More framing of the basement.
July 22, 2005   Framing is started in the basement.
July 19, 2005   Framing the crawl space.
July 18, 2005   The concrete is cured, starting the framing.
July 16, 2005   Pouring of the basement floor and crawl space.
July 14, 2005   Creation of support forms and installation of a vapour barrier in preparation for pouring of the basement floor.
July 12, 2005   Tamping of basement floor and terrace area in preparation for pouring of the basement floor. Plumbing is now installed.
July 7, 2005   Back filling of the foundation walls, installation of plumbing.
June 29, 2005   Waterproofing of the foundation walls, installation of drain pipes and crushed rock.
June 27, 2005   Removing of more wall forms. It is starting to look like a foundation!
June 24, 2005  

The concrete is dry. The beginning of removing the foundation wall forms.

June 23, 2005   The concrete pour of building foundation.
June 22, 2005   Installing last of building foundation wall forms and blocking in preparation for concrete pour.
June 20, 2005   Installing more inside foundation wall forms and work on rebar.
June 17, 2005   Building inside foundation wall forms.
June 14, 2005   More building outside foundation wall forms and installation of rebar.
June 10, 2005   More building outside foundation wall forms.
June 9, 2005   Stripping of the concrete foundation forms and beginning of building outside foundation wall forms.
June 8, 2005   The BIG pour of concrete into the foundation forms.
June 7, 2005   More rebar installation and more building of concrete foundation forms.
June 6, 2005   Installation of rebar in concrete foundation forms.
June 4, 2005   Installation of piping for electrical service.
June 3, 2005   Further progress on building of concrete foundation forms.
June 2, 2005   Building of concrete foundation forms and crushed rock driveway.
June 1, 2005   Building of concrete foundation forms.
May 31, 2005   Finish concrete re-enforcement of underpinnings for Ocean Park Dental building and beginning to lay out foundation forms.
May 30, 2005   Concrete re-enforcement of under-pinnings for Ocean Park Dental building.
May 27, 2005   Drilling of underpinnings for Ocean Park Dental building and injection of concrete.
May 25, 2005   Installation of phone line to construction trailer and delivery of framing lumber for basement footings.
May 19, 2005   Installation of gravel in restaurant basement and painted site lines.
May 18, 2005   Protection of excavation of restaurant basement by Ocean Park Dental building.
May 17, 2005   More excavation of restaurant basement.
May 16, 2005   Excavation of restaurant basement and laying out of site lines.
May 14, 2005   Tamping parking lot and excavation of restaurant building site.
May 13, 2005   Tamper on site, contractor conference and top soil storage.
May 12, 2005   Installing sand mix for parking lot and more excavation of restaurant building site.
May 11, 2005   Excavation of restaurant building site and laying foundation for parking lot.
May 10, 2005   Breaking up concrete and laying foundation for parking lot.
May 9, 2005   Organizing of restaurant building debris.
May 6, 2005   Tear down of main restaurant building.
May 5, 2005   Loading and carting away of house debris.
May 4, 2005   Tear down of the two houses.
April 28, 2005  

Preparation of the two houses for tear down. Clearing of the brush.

April 25, 2005  

Moving day pictures

September 25, 2003   "Before" pictures